City of West Memphis issued the following announcement on July 24.
(7/23/21) Contractors are progressing on the phase three repairs. There is now a total of 17 plates. Thirteen of the 17 plates have been at least “rough-set.” The last four plates are arriving today and will be set over the next few days. Aside from the drilling, bolting, and torqueing, installation of these plates is a process that also involves the removal of the lateral bracing, modification of the gusset connection plate, and reinstallation of the lateral bracing. Once the last bolt is torqued on the plate, these items can be completed. This work will likely push us into the first part of August in opening the bridge to traffic. TDOT says they will have more of a specific schedule next week.
Original source can be found here.
Source: City of West Memphis